Transmission system models provide the foundation for MISO’s planning processes. Reliability (Powerflow and Dynamics) models support the core planning functions necessary to ensure compliance with the MISO Tariff and North American Electric Reliability Corporation (NERC) standards. MISO employs a collaborative, stakeholder-driven process to develop assumptions that ensure appropriate modeling of future transmission system scenarios. Models are also coordinated with MISO’s neighboring entities through the NERC Multi-regional Modeling Working Group (MMWG) to ensure systems are accurately represented across its seams.
MISO develops annual models using stakeholder data for a variety of near-term and long-term planning studies; models represent a 10-year planning horizon. The modeling process runs from September to the following August.
Model | Modeling Tool |
Powerflow
|
|
Dynamics
|
|
Date | Milestone | Responsible Party |
08/25/2023 | LSE, TO, and GO data request sent | MISO |
08/25/2023 | Model On Demand reference models posted | MISO |
09/08/2023 | Generator data due to Model On Demand | GO |
09/22/2023 | Load profiles due to Model On Demand | LSE |
09/22/2023 | Transmission project, BLG profile and device profile data due to Model On Demand | TO, RP |
10/13/2023 | Topology and Load Pass model posted for review | MISO |
10/13/2023 - 10/27/2023 | Review Topology and Load Pass models/updates to MOD | LSE, TO, RP, and GO |
12/15/2023 | Review Pass 3 models posted for review | MISO |
12/15/2023 | Review of Review Pass models, respond to data checks/updates to MOD | LSE, TO, RP, and GO |
03/15/2024 | Final MISO models completed/posted | MISO |
Date | Milestone |
04/12/2023 | MISO issues Dynamics Data Request |
04/28/2023 | Stakeholders complete Dynamics Data Request |
06/09/2023 | Stakeholders comments due on Dynamics cases |
06/12/2023 | MISO incorporate changes from stakeholder comments |
06/15/2023 | MISO post final PSS/e and TSAT Dynamics cases |